İÇ ANADOLU CCPP – 380 kV AIS SUBSTATION
PROJECT NAME : IC ANADOLU CCPP 380 KV AIS SUBSTATION
PLACE : KIRIKKALE / TURKEY
CLIENT : GAMA POWER
MAIN CONTRACTOR : ALSTOM GRID ENERJI AS
SCOPE OF WORK :
6 FEEDERS 380 KV SUBSTATION INSTALLATION
- STEEL ERECTION
- PRIMARY EQUIPMENT INSTALLATION
- SECONDARY INSTALLATION ( PANEL INSTALLATION, CABLING, TERMINATION ETC.)
- PRIMARY & SECONDARY EQUIPMENT TESTING
- OVER ALL COMMISSIONING
- COMPLETED AT JULY, 2015