DHI-QAR 750MW CCPP – 132kV AIS SUBSTATION
PROJECT NAME : DHIQAR – ENKA 4 x 125 MW CCPP – 132 KV AIS SWITCHYARD SS
PLACE : NASIRIYYE – DHIQAR / S. IRAQ
CLIENT : MINISTRY OF ELECTRICITY 0F IRAQ
MAIN CONTRACTOR : ENKA UK CONSTRUCTION – GE POWER CONSOURTIUM
SCOPE OF WORK : |
21 FEEDER 132 KV AIR INSULATED SUBSTATION INSTALLATION · STEEL ERECTION · PRIMARY EQUIPMENT INSTALLATION · SECONDARY INSTALLATION ( PANEL INSTALLATION, CABLING, TERMINATION ETC.) · LOOP TEST PRIOR TO FUNCTION TEST · PRIMARY & SECONDARY TESTING & COMMISSIONING · COMPLETED AT FEBRUARY, 2020 |